Experiencia
Maintenance of Pipeline Platforms
PROJECT DESCRIPTION:
Contract ONSM-048/00
A detailed inspection of the underwater section was conducted, focusing on the welds and cathodic protection. In the superstructure of the platform, structural members such as railings, stairs, and floors were replaced. Additionally, sandblasting and painting systems were applied.
More projects
Platform "CLON" Operating in the Costa Rican Caribbean
Clone working in the Costa Rican Caribbean in the Moin port for the North American company CH2M HILL, carrying out soil mechanics studies…
Displacement of Submarine Material for the MENADRILL II
Desplazamiento de material submarino en el muelle de CELASA (MENAdrill I) (Buceo) Bajo el sistema e inspección, por el método de partículas magnéticas.